Updates
19/01/2022 15:39
Commissioning is now complete and the lock is now operational. Apologies again for the delay.
19/01/2022 09:45
Please accept our apologies for our delayed update.
Due to some unforseen issues on site the re-opening of the lock has been delayed. We are finalising the commissioning today and plan to have the lock fully operational by the end of today.
16/12/2021 16:21
This Stoppage has been extended. Unfortunately due to additional commissioning work, this stoppage will now be completed on 14th January. This Stoppage will now end 14/01/2022. We apologise for any inconvenience caused.
13/12/2021 14:35
13/12/2021:
This Stoppage has been extended. Unfortunately we have had to extend this Stoppage, this is due to a delay in delivery of key components required. This Stoppage will now end at 16.00 21/12/2021. We apologise for any inconvenience caused.