21/10/2021 15:52
Due to unforeseen circumstances during the installation of the bridge by the contractors and its not yet safe to open the towpath.
19/08/2021 11:47
Due to unforeseen circumstances the towpath will remain shut until the 1st of October in order to complete works.
26/07/2021 15:42
Due to unforeseen circumstances the towpath will remain shut for another 4 weeks in order to complete works.
There is a diversion route in place for towpath users.
11/05/2021 16:05
change to dates.
The start date is 17May 2021, and the opening date is 26 July 2021.