Updates
08/04/2021 08:35
The canal was planned to be reopened on the 7th April, but further monitoring of the canal is required to ensure safety ahead of reopening. The canal and towpath will now be reopened at 6pm on Saturday 10th April.
01/04/2021 08:26
Following completion of the canal bed repair works at Ivy House Embankment, the canal and towpath closure needs to be extended to the 7th April in order to test and monitor the situation and confirm the safety of the canal ahead of reopening. Reopening is now planned to be at 6pm on Wednesday 7th April.
25/03/2021 10:57
Additional areas of canal bed repair works have had to be undertaken at Ivy House Embankment. Unfortunately, this will delay the planned reopening. These works will now be completed in time to allow the canal to be reopened at 18:00 on the 31st March.
26/02/2021 16:14
The canal has been dewatered between Ivy House Road Lift Bridge and Bucknall Road bridge for investigation purposes. An inspection carried out on the 22nd February indicated that works were required to be undertaken in the bed of the canal before it can be refilled and fully reopened to boat traffic. Works will commence immediately, so closures of the canal and towpath will remain in place for the safety of the public and we intend to reopen the canal and towpath on the 29th March 2021 at 6pm.
18/02/2021 13:04
Please be advised the towpath is only closed between Bridge 11 Ivyhouse Road Lift Bridge and Bridge 13 Cromer Road.
The navigation is closed from Bridge 1, Etruria Footbridge to Bridge 13 Cromer Road.