Aubrey's Lift Bridge, Bridge 221, Thrupp, Oxford Canal.

Starts: 1 March 2021 08:00 am

Ends: 12 March 2021 04:00 pm inclusive

Type: Navigation Closure

Reason: Repair

Is the towpath closed? No

Location

Closest waterwayOxford Canal
Starts atBridge 221, Aubreys Lift Bridge
Ends atBridge 221, Aubreys Lift Bridge
Upstream winding holeThrupp Wide, before Bridge 221.
Downstream winding holeBridge 243, Isis Lock.

Updates

21/12/2020 12:21

The repairs to Aubrey's Lift Bridge at Thrupp, which were previously postponed, have now been re-programmed for the new year to tie in with our stoppage at Dukes Lock and Bridge 233.

The navigation will now be fully closed at Thrupp from Monday 1st March until Friday 12th March 2021. The towpath will remain open during the works.

From 12th March until 31st March 2021, there will be restricted passage whilst repairs to the bridge are completed.

Further information will be published early in the new year.

04/12/2020 11:57

We are sorry to report that repairs to Aubrey's Lift Bridge have not been able to start as hoped, due to continuing issues with the supply of materials and equipment required by our contractors to carry out the work. As a result, this stoppage will have to be deferred until the new year, and we hope to begin work in mid January, at the same time as our closure at Dukes Lock and Bridge 233. As soon as we have confirmed dates and further information, we will re-publish this notice. In the meantime, the navigation will remain open and the bridge can be used as normal. Please accept our sincere apologies for any confusion caused by this change to the planned work.

11/11/2020 15:21

Due to unexpected delays in the delivery of essential electrical equipment, we will be unable to start work at Aubrey's Lift Bridge until 16th November.

The end date of the closure will not be affected, as the installation of the equipment will not take as long as originally anticipated.

We apologise for any inconvenience this delayed start may have caused.

Description

A stoppage is required for the installation of new hydraulic, electrical and traffic control systems.

01/06/2020: The information above is a draft notice of works planned as part of our winter 2020/21 stoppages programme. This is subject to change depending on the latest advice from the UK government on coronavirus. Please follow our guidance relating to coronavirus when using the canals and towpaths https://canalrivertrust.org.uk/coronavirus.

photo of a location on the canals
newsletter logo

Stay connected

Sign up to our monthly newsletter and be the first to hear about campaigns, upcoming events and fundraising inspiration