Lock 6, Grindley Brook, near Whitchurch, Llangollen Canal

Detail

From Date: 02/11/2020 08:00

To Date: 18/12/2020 16:00 inclusive

Type: Navigation Closure

Reason: Repair

Is the towpath closed? No

Location

Closest waterway: Llangollen Canal

Starts at: Lock 6, Grindley Brook Locks

Ends at: Lock 6, Grindley Brook Locks

Upstream winding hole: Between Bridges 30 and 31.

Downstream winding hole: Near Bridge 22.

Description

Works will include bottom gate refits, ladder improvements and re-surfacing of the lock-tail ramp.

01/06/2020:  The information above is a draft notice of works planned as part of our winter 2020/21 stoppages programme.  This is subject to change depending on the latest advice from the UK government on coronavirus.  Please follow our guidance relating to coronavirus when using the canals and towpaths https://canalrivertrust.org.uk/coronavirus.

Comments

12/07/2020 11:49 - Canal & River Trust

Thank you for your comments. We appreciate everyone’s concerns and the need to keep, as much as we can, some routes open during the winter. In this area we have tried to find the best options for the Llangollen, Shropshire Union, Middlewich Branch and Trent & Mersey Canals as a whole, and the many stakeholders who will be affected. This has to be balanced with working out the best programme for our construction teams, including the logistics of moving plant, equipment and materials from site to site, as well as the amount of time available (pre or post Christmas) to carry out the repairs needed at each location. Following the first phase of consultation we have made some changes to the programme, including deferring two stoppages on the Trent & Mersey Canal. Unfortunately, however, it hasn't been possible to change the dates for closures on the Llangollen.

04/06/2020 14:49 - Chas Hardern Boats

As the Llangollen was closed all of last winter and all hire companies have lost at least half of their income this season cannot this stoppage be done at the same time as Chirk to allow boating until after Christmas otherwise Llangollen will in effect be closed for the whole of another winter.

03/06/2020 19:19 - Richard Chamberlain

Could the stoppages at this end of the llangollen canal be done at the same time as Chirk Tunnel?, This would leave Navigation open until after Christmas,rather than closed all winter.