Updates
09/02/2021 11:33
Unfortunately, due to further delays with the delivery from Europe of essential parts for the new hanger rods, we will be unable to start repairs at Top Lane, Kirkhouse Green and Sykehouse Road Lift Bridges when expected.
However, additional teams will be brought in to assist on the project and we will work through the weekends to enable the repairs to be completed as quickly as possible.
The revised dates for this stoppage are now 5th to 25th March 2021.
21/12/2020 13:27
Unfortunately, issues and delays with the delivery of some key parts for the replacement hanger rods means our programme of works for lift bridge repairs has been affected, and our stoppage dates need to be put back.
Please note the revised dates for this closure.