Jordan Bridge- Strengthening the Bridge

Detail

From Date: 18/03/2020 08:00

To Date: 15/06/2020 19:00 inclusive

Type: Navigation Restriction

Reason: Information

Is the towpath closed? No

Location

Closest waterway: Sheffield & South Yorkshire Nav

Starts at: Jordan Bridge 21

Ends at: Jordan Bridge 21

Updates

26/03/2020 10:00

Customers are asked to only move if essential to reach services and to follow government guidance at all times.

17/03/2020 14:41

We have been advised that the works to the West side of the waterway will now take place with effect from  18/03/2020.

Description

Third party contractors are strengthening the bridge.

The waterway will be partially closed as follows:

25/3/2020 to 18/05/2020 West side of the waterway

19/05/2020 to 15/06/2020 East side of waterway

Boaters should slow down when approaching the bridge and follow the signage as to which side to use.