From Date: 21/06/2019 00:00

To Date: 03/07/2019 11:16 inclusive

Type: Towpath Closure

Reason: 3rd Party Works

Is the towpath closed? Yes

Location

Closest waterway: Leeds & Liverpool Canal

Starts at: Bridge 130, Sandygate Bridge

Ends at: Bridge 130B, Manchester Road Bridge

Updates

03/07/2019 11:16

We are pleased to advise the third party works are complete and the towpath is now open.

24/06/2019 15:23

The towpath will remain closed whilst third-party works continue to an adjacent building. In the interest of public safety, we politely request all canal users to listen to any advice that may be given by the onsite banksmen and be prepared to stop if requested. This is to allow the third-party contractors to radio through to the demolition team to cease works at the adjacent building to allow for a safe passage.

Description

Due to third-party works, an emergency towpath closure has been implemented between Bridge 130, Sandygate Bridge and Bridge 130B, Manchester Road Bridge, on the Leeds and Liverpool Canal.

An update will be provided Monday 24 June.