Between bridges 80 and 81. Selly Oak Birmingham

Detail

From Date: 03/07/2019 09:30

To Date: 03/07/2019 10:00 inclusive

Type: Navigation Restriction

Reason: Maintenance

Is the towpath closed? No

Location

Closest waterway: Worcester & Birmingham Canal.

Starts at: Bridge 80, Bristol Road

Ends at: Bridge 81, Selly Oak Railway Bridge

Updates

13/06/2019 14:45

A change in hours for the lift.

They will now be between 18.00 - 22.00 hrs

Description

A temporary footbridge that is connecting the
developers site office on the off side of the canal to the new development on the towpath side is to be removed, the lift is planned for the evening of the 3rd
July.

Although the towpath and navigation will remain open, due to Health and Safety a short delay of 20 minutes will be encountered for craft and towpath user’s.

Banksmen will be on the towpath either side of bridge a safe distance away to
restrict passage while the lift takes place.