Sluice 5 at Lock 10 Ganny, near Brighouse, Calder & Hebble Navigation

Detail

From Date: 03/02/2020 08:00

To Date: 06/03/2020 16:00 inclusive

Type: Navigation Closure

Reason: Repair

Is the towpath closed? No

Location

Closest waterway: Calder & Hebble Navigation

Starts at: Lock 10, Ganny

Ends at: Lock 10, Ganny

Upstream winding hole: Downstream of Lock 5, Woodside Mills

Downstream winding hole: Junction with Huddersfield Broad Canal

Updates

19/02/2020 11:02

Although works have progressed well at Lock 10 Ganny, our team has been hampered by water levels which are preventing the re-fixing of the sluice. 

As a result, we need to extend the stoppage by up to one week, until 6th March. 

We apologise for any inconvenience this may cause and appreciate your patience during these extremely difficult conditions.

Description

General Repairs to the sluice next to Lock 10 including repairs to the gearing frame and damaged door