Bridge 1C

Detail

From Date: 28/12/2018 00:00

To Date: 29/06/2019 00:00 inclusive

Type: Navigation Restriction

Reason: 3rd Party Works

Is the towpath closed? No

Location

Closest waterway: Nottingham & Beeston Canal

Starts at: Bridge 1c, Lms Main Line No 25

Ends at: Bridge 1c, Lms Main Line No 25

Updates

30/04/2019 09:30

As part of the Bridge replacement works, J Murphy & Sons working on behalf of Network Rail will be have a pontoon and scaffolding system in the offside navigational channel, extending approximately 1m into the main (Towpath side) navigational channel. 

The pontoon and scaffolding will be in-situ for the duration of the works. The main, towpath side channel will remain open with reduced width.     

We have now been advised by J Murphy & Sons the works will be completed on the 29th June.

Description

As part of the Bridge replacement works, J Murphy & Sons working on behalf of Network Rail will be have a pontoon and scaffolding system in the offside navigational channel, extending approximately 1m into the main (Towpath side) navigational channel. 

The pontoon and scaffolding will be in-situ for
the duration of the works. The main, towpath side channel will remain open with reduced width.     

We are still awaiting for confirmation of the end date, once we have more information we will update the notice accordingly.