Bridge 1c, Nottingham, of the Nottingham & Beeston Canal
Detail
From Date: 28/12/2018 05:00
To Date: 01/02/2019 20:00 inclusive
Type: Navigation Restriction
Reason: 3rd Party Works
Is the towpath closed? No
Location
Closest waterway: Nottingham & Beeston Canal
Starts at: Bridge 1c, Lms Main Line No 25
Ends at: Bridge 1c, Lms Main Line No 25
Description
As part of the bridge deck replacement works, J Murphy & Sons, working on behalf of Network Rail, will have a pontoon and scaffolding system in the offside navigational channel, extending approximately 1m into the main (towpath side) navigational channel. The towpath side channel will remain open with reduced width.
Please be aware the navigational width during the works will be approximately 6m under the bridge.
The pontoon and scaffolding will be in-situ for the duration of the works.
We have worked closely with Network Rail to minimise disruption during the bridge deck replacement works. There are a number of separate elements affecting the navigation. Individual notices will be raised for each element, which are as follows:
12/11/2018 to 24/12/2018 Navigation restriction
01/12/2018 to 02/12/2018 Overnight closure
08/12/2018 to 09/12/2018 Overnight closure
15/12/2018 to 16/12/2018 Overnight closure
24/12/2018 to 28/12/2018 Navigation closure
28/12/2018 to 01/02/2019 Navigation restriction