To facilitate the demolition of the two footbridges and installation of a surface water diversion (agreement with Network Rail)
Reason for Extension:
Due to over running works with the major Bridge and Viaduct Construction known as Ordsall Chord, over the river Irwell.
Delays had a knock-on effect and pushed the minor works that effect the CRT Remit to the end of the programme.