Railway Bridge (Bridge 23), Lee Navigation, Tottenham

Detail

From Date: 25/07/2016 07:00

To Date: 31/03/2017 19:00 inclusive

Type: Towpath Closure

Reason: 3rd Party Works

Is the towpath closed? No

Location

Closest waterway: Lee Navigation

Starts at: Bridge 23 (Railway)

Ends at: Bridge 23 (Railway)

Updates

23/11/2016 16:11

The towpath beneath Bridge 23 on the Lee Navigation will be affected by Network Rail's bridge works from July 2016 to March 2017.

Route A is through Ferry Lane Estate and will be in place until 15 January 2017.

Route B is on a pontoon on the water and will be in place from 16 January to 31 March 2017.

19/09/2016 15:09

The towpath beneath Bridge 23 on the Lee Navigation will be affected by Network Rail's bridge works from July 2016 to March 2017.

Route A is through Ferry Lane Estate and will be in place from 25 July to 23 September.

Route B is on a pontoon on the water and will be in place from 24 September to 25 November.

Route A through Ferry Lane Estate will then be in force again from 26 November to 6 January 2017.

Route B, the pontoon, will then be in force again from 7 January 2017 to 31 March.

Please see local signs.

19/09/2016 15:09

The towpath beneath Bridge 23 on the Lee Navigation will be affected by Network Rail's bridge works from July 2016 to March 2017.

Route A is through Ferry Lane Estate and will be in place from 25 July to 23 September.

Route B is on a pontoon on the water and will be in place from 24 September to 25 November.

Route A through Ferry Lane Estate will then be in force again from 26 November to 6 January 2017.

Route B, the pontoon, will then be in force again from 7 January 2017 to 31 March.

Please see local signs.

19/09/2016 15:06

02/08/2016 09:48

The towpath beneath Bridge 23 on the Lee Navigation will be affected by Network Rail's bridge works from July 2016 to March 2017.

Route A is through Ferry Lane Estate and will be in place from 25 July to 23 September.

Route B is on a pontoon on the water and will be in place from 24 September to 25 November.

Route A through Ferry Lane Estate will then be in force again from 26 November to 6 January 2017.

Route B, the pontoon, will then be in force again from 7 January 2017 to 31 March.

Please see local signs.

Description

For Network Rail's bridge works, the towpath is to be closed and replaced with a floating pontoon beneath Railway Bridge 23 on the Lee Navigation in Tottenham. Please take care. This will be from July 2016 to February 2017.

Before the pontoon is installed, Network Rail need to work on the river wall and will have to close the towpath for 3 weeks from 25 July to 19 August 2016. A diversion will be in place. Please follow local signs.