Lock 82, Benham Lock

Notice Details
From Date:
4th January 2017
To Date:
3rd February 2017 at 09:53 inclusive
Type:
Navigation Closure
Reason:
(Re)Construction
Notice updates:
03/02/2017 @ 09:53
The works have been completed and the navigation is now open.
18/01/2017 @ 16:24

The stoppage is to carry out lock gate quoin repairs.

Please be advised that, due to unforeseen mobilisation issues with equipment, some elements of the stoppage works have been delayed by two weeks.

We will be working extended hours and weekends to recover as much of this time as possible.  However, as a result, there will be a delay in reopening of two days.

Description:

To carry out lock gate quoin repairs.

Location:
Kennet & Avon Canal
Starts At:
Lock 82, Benham Lock
Ends At:
Lock 82, Benham Lock
Up Stream Winding Hole:
Hamstead Winding Hole, above lock 81, Hamstead Lock
Down Stream Winding Hole:
West Mills Winding, above lock 85, Newbury Lock