Conisbrough Railway Bridge

Notice Details
From Date:
3rd May 2016 at 07:00
To Date:
30th October 2016 at 19:00 inclusive
Navigation Restriction
3rd Party Works
Notice updates:
15/09/2016 @ 09:49

We have been advised by the Contractor that these works have been extended until 30 October.

10/08/2016 @ 14:31

The Contractor has discovered additional repairs which require attention whilst the scaffolding is still in place on the structure. Therefore the works are now due to finish on the 30th of September

21/06/2016 @ 11:39

We have been advised by the Contractors that the scaffolding works are taking longer than expected and the works are now due to finish on 12 August.


Contractors (Dyer & Butler) are carrying out bridge repair works using a scaffold supported from the bridge. The watercourse will be restricted at this location at points due to the delivery of materials from a barge.  All boat traffic should take caution when passing and abide by the contractors advice, this may result in delay of no longer than 15-20 minutes

Sheffield & South Yorkshire Navigations
Starts At:
Railway Bridge
Ends At:
Railway Bridge