Leeds Bridge Investigation Works
Detail
From Date: 05/11/2018 09:00
To Date: 20/12/2018 17:00 inclusive
Type: Navigation Restriction
Reason: 3rd Party Works
Is the towpath closed? No
Location
Closest waterway: Aire & Calder Navigation Main Line
Starts at: Leeds Bridge
Ends at: Leeds Bridge
Updates
27/11/2018 11:22
The contractor is continuing these works on the bridge until Christmas.
A separate notice will be issued after Christmas for extensive painting works.
05/11/2018 15:36
We have been advised by the contractors that work will be carried out on site for 4 weeks instead of 2 weeks.
Description
There will be a navigation restriction in place for Leeds Bridge in order to facilitate AE Yates undertaking paint testing on a local authority bridge.
They will be cleaning and painting a section of the bridge using a 6m x 6m pontoon to the edge of the navigation.
Boaters and other navigation traffic may be affected for up to 20 minutes to enable the pontoon to move out of the way. Please slow down on approaching the bridge.