Gloucester and Sharpness Canal Towpath Closure

Detail

From Date: 24/09/2018 00:00

To Date: 28/11/2018 23:59 inclusive

Type: Towpath Closure

Reason: Maintenance

Is the towpath closed? Yes

Location

Closest waterway: Gloucester & Sharpness Canal

Starts at: Bridge 18, Rea Swing Bridge

Ends at: Access Point-Midsummer Walk

Updates

28/11/2018 15:26

Please be advised that the towpath is now fully open between Rea Bridge and Midsummer Walk as the first phase of laying tarmacadam has been completed ahead of schedule.

Certain lengths will be closed during the spring of 2019 when the weather is favourable in order to install the buff-coloured surface dressing. We will advise of the dates of these closures nearer to the time.

For further information or advice, please contact the Gloucester Dock Office on 01452 318012 or at [email protected].

Thank you.

02/11/2018 17:21

Please be advised that works between Sellars Bridge and Rea Bridge, and Rea Bridge and Sims Bridge has been completed ahead of schedule and the towpath in these areas is now open.

As a result the next stage of the works has been brought forward and over the coming week the towpath between Sims and Netheridge Bridges will be closed for a period of time, as well as between Netheridge and Hempsted.

All other closures remain consistent with the dates previously specified.

For further information please contact the Gloucester Dock Office on 01452 318012 or at [email protected].

Thank you for your co-operation in this matter.

05/10/2018 15:58

Please be advised that whilst the towpath improvement works are ongoing, for the safety of all users there will be no access to the towpath along the lengths of canal between Rea and Hempsted Bridges in places where the works are being carried out.

The towpath will however be reopened at the weekend to all users and access to moorings will be available during this time.

All other staged towpath closures remain as previously specified.

For further information please contact the Gloucester Dock Office on 01452 318012 or at [email protected].

Thank you for your co-operation in this matter.

01/10/2018 12:16

Please be advised the towpath between Rea and Hempsted Bridge will now be closed from 24th September 2018 to 15th February 2019 for the safety of all users whilst towpath improvement works are being carried out.

The towpath will be closed in stages as listed below. However, please be aware that these dates are not fixed and are subject to change. Please only use them as a rough guide when planning your journey.

24/09/18 - 12/10/18 - closed from Rea Bridge to 200m south.

25/09/18 - 09/11/18 - closed from Rea Bridge to Sims Bridge.

22/10/18 - 30/11/18 - closed from Sims Bridge to Netheridge Bridge.

12/11/18 - 08/01/19 - closed from Netheridge Bridge to Hempsted Bridge.

17/12/18 - 15/02/19 - closed from Hempsted Bridge to Midsummer Walk.

Gloucestershire City Council has received funding to greatly improve the towpath for a length of 3.5 kilometres. The benefits will see the majority of towpath widened with an improved surface, suitable for use in all weathers.

We hope these improvements will encourage people to use the towpaths on their daily commute as well as for a means of relaxing and will leave the busy roads behind!

For further information please contact the Gloucester Dock Office on 01452 318012 or at [email protected].

Thank you for your co-operation in this matter.

05/09/2018 13:14

Please be advised the towpath between Rea and Hempsted Bridge will be closed from 24th September to 22nd December for the safety of all users whilst towpath improvement works are being carried out.

Gloucestershire City Council has received funding to greatly improve the towpath for a length of 3.5 kilometres. The benefits will see the majority of towpath widened with an improved surface, suitable for use in all weathers.

We hope these improvements will encourage people to use the towpaths on their daily commute as well as for a means of relaxing and will leave the busy roads behind!

Thank you for your co-operation in this matter.

For further information please contact the Gloucester Dock Office on 01452 318012 or at [email protected].

03/08/2018 10:07

Please be advised the towpath between Rea and Hempsted Bridge will be closed from 1st October to 22nd December for the safety of all users whilst towpath improvement works are being carried out.

Gloucestershire City Council has received funding to greatly improve the towpath for a length of 3.5 kilometres. The benefits will see the majority of towpath widened with an improved surface, suitable for use in all weathers.

We hope these improvements will encourage people to use the towpaths on their daily commute as well as for a means of relaxing and will leave the busy roads behind!

Thank you for your co-operation in this matter.

For further information please contact the Gloucester Dock Office on 01452 318012 or at [email protected].

Description

Please be advised the towpath between Rea and Hempsted Bridge will be closed from 28th August to 22nd December (subject to change), for the safety of all users whilst towpath improvement works are being carried out.

Gloucestershire City Council has received funding to greatly improve the towpath for a length of 3.5 kilometres. The benefits will see the majority of towpath widened with an improved surface, suitable for use in all weathers.

We hope these improvements will encourage people to use the towpaths on their daily commute as well as for a means of relaxing and will leave the busy roads behind!

Thank you for your co-operation in this matter.

For further information please contact the Gloucester Dock Office on 01452 318012 or at [email protected].