Between Penawr Bridge 150 and Cross Oak Bridge 147, Monmouthshire & Brecon Canal
Detail
From Date: 04/02/2019 08:00
To Date: 15/03/2019 16:00 inclusive
Type: Navigation Closure
Reason: Repair
Is the towpath closed? No
Location
Closest waterway: Monmouthshire & Brecon Canal
Upstream winding hole: Pencelli Bridge 154
Downstream winding hole: Talybont Wharf
Updates
20/12/2018 17:04
Our engineers have reviewed the design of the works to repair the failed timber edge between Penawr Bridge 150 and Cross Oak Bridge 147. We are pleased to confirm this has resulted in a revised methodology which means the duration of the navigation closure has been reduced to just six weeks. Please note the new start date for the stoppage.
Description
Repairs to failed timber edge |