Unfortunately the works at Saltersford Lock have encountered further delays since our last update, but we have now found a solution to the issues preventing a seal on the downstream stop planks. The lock has now been pumped down allowing us to fully inspect the structure and commence the repairs urgently needed to the cill and gates. We apologise that our revised date for re-opening the navigation to customers has been pushed out to 17th May 2019.

Dewatering the lock has been a huge challenge for our operatives, requiring installation of 9 separate large blanking plates, 6 props across the lock chamber, top and bottom stop planks and repairs to a damaged downstream cill, all of which have been done underwater by divers to facilitate pumping the water out. Having reached this stage of the project, we need to be able to take this opportunity to return the lock to an operable condition. The scale of problems we have experienced have been unforeseen, but nonetheless reflect the complexity of dewatering a large river lock of deteriorated condition.

We apologise for this ongoing closure, and thank customers for their continuing patience with us.  

 

06/03/2019 @ 10:57

Unfortunately the works at Saltersford Lock have encountered unforeseen problems with its structural condition during the dewatering phase. This has resulted in a delay to the project, and the earliest date when we hope to be able to re-open the navigation to customers is now by close of play on 18th April 2019.

All preparatory works are being carried out underwater by divers, so there are obvious complexities associated with this.  The floor on the downstream approach to the lock has been found to be badly damaged and this is currently preventing installation of the downstream stop planks until a solution is implemented.  Urgent works are ongoing to try and resolve this issue in order that the lock can be dewatered, thoroughly inspected and repaired as necessary in order to facilitate its future operable condition. 

We apologise for this ongoing closure, and are progressing the dewatering (and subsequent repairs) as soon as we can.

Description:
Lock closure and dewatering, for large scale repairs and maintenance.  Please be aware the end date of this closure is outside our published winter stoppage period.
Location:
Weaver Navigation
Starts At:
Saltersford Large Lock
Ends At:
Saltersford Large Lock
Up Stream Winding Hole:
River Weaver
Down Stream Winding Hole:
River Weaver
Search again

Notice Location