Lock 3, Aston Lock, near Aston on Trent, Trent and Mersey Canal

Notice Details
From Date:
7th January 2019 at 08:00
To Date:
24th March 2019 at 16:00 inclusive
Type:
Navigation Closure
Reason:
Repair
Notice updates:
08/03/2019 @ 08:22

Unfortunately, we will be unable to complete the repairs needed at Aston Lock 3 as we had hoped and planned.  

We have had considerable additional work to do including the complete replacement of quoins and collars on all the gates, followed by the replacement of the top and bottom gates, as well as extensive brickwork repairs to the lock chamber walls.  

The team has been working hard to complete this work as advertised (including working at weekends) but more time is needed to finish all the additional repairs required.  

It is now expected the navigation will re-open on Sunday 24th March.   We sincerely apologise for this delay.

27/11/2018 @ 16:03

Additional works have been identified at Aston Lock 3 which require an extension to the duration of the navigation closure.

In addition to general repairs and improvements to the locks, new quoins will be installed prior to the replacement of the top and bottom lock gates.  

 

Description:
Replacement of the top and bottom lock gates needed and general repairs to the lock 
Location:
Trent & Mersey Canal
Starts At:
Lock 3, Aston Lock
Ends At:
Lock 3, Aston Lock
Up Stream Winding Hole:
Sarson's Bridge 11
Down Stream Winding Hole:
Shardlow, near Bridge 2