Bridge 142 Graig-Las to Bridge 131 Yard Bridge
Detail
From Date: 13/11/2017 08:00
To Date: 15/12/2017 16:00 inclusive
Type: Navigation Closure
Reason: Repair
Is the towpath closed? No
Location
Closest waterway: Monmouthshire & Brecon Canal
Starts at: Bridge 142, Graig-Las Bridge
Ends at: Bridge 131, Yard Bridge
Upstream winding hole: Bridge 142, Graig-Las
Downstream winding hole: Bridge 131, Yard Bridge
Description
Extensive repairs to be carried out to the
waterway wall to prevent leakage.
This notice replaces number 10606 which is capturing the same length and more to enable the delivery teams to repair
the highest priority leaks.
The start date of this new closure will be 7 days later than originally planned to allow time to work on the increased scope.