Lock 12, Brighouse, Calder & Hebble

Notice Details
From Date:
8th January 2018 at 08:00
To Date:
12th February 2018 at 16:00 inclusive
Type:
Navigation Closure
Reason:
Repair
Notice updates:
02/02/2018 @ 13:26

Unfortunately our progress on site at Locks 11 and 12, Brighouse, has been severely hampered in the last two weeks as a result of flood water levels.  This means we will not be able to complete our work within the original programme. 

It will be necessary, therefore, to extend the closure by one week, until 12th February. 

We will do everything we can to reduce this timescale and sincerely apologise for any inconvenience caused.

Description:

Gate relining works to reduce leakage

Location:
Calder & Hebble Navigation
Starts At:
Lock 12, Brighouse Bottom
Ends At:
Lock 12, Brighouse Bottom
Up Stream Winding Hole:
Winding hole downstream of Woodside Lock
Down Stream Winding Hole:
Junction of the Calder & Hebble Navigation