Lock 11 Brighouse, Calder & Hebble

Notice Details
From Date:
8th January 2018 at 08:00
To Date:
5th February 2018 at 16:00 inclusive
Type:
Navigation Closure
Reason:
Repair
Notice updates:
24/10/2017 @ 10:56

Following further review, the closure to carry out repairs and relining at Lock 11, Brighouse, will now take place after Christmas. 

The dates will tie in with the closure at Lock 12 to allow a more efficient use of local resources.

26/09/2017 @ 16:20

Repairs at Lock 10 will be deferred until Winter 2018/19 to allow resources to be re-directed to more urgent arising high priority works. 

Works at Lock 11 are not affected and will go ahead as planned.

Description:

Repair and relining works to the lock gates and fender replacement.

In order to meet local customer requirements, the works have been re-programmed to pre-Christmas to allow the Fearns Lock 1 (Aire & Calder) closure to be moved back to post-Christmas.

 

Location:
Calder & Hebble Navigation
Starts At:
Lock 11, Brighouse Top
Ends At:
Lock 11, Brighouse Top
Up Stream Winding Hole:
Winding Hole downstream of Woodside Lock
Down Stream Winding Hole:
Junction to the Calder & Hebble Navigation