Claydon Top Lock 17, Oxford Canal

Notice Details
From Date:
27th November 2017 at 08:00
To Date:
13th December 2017 at 14:16 inclusive
Type:
Navigation Closure
Reason:
Repair
Notice updates:
13/12/2017 @ 14:16
We are pleased to advise that all repair works throughout the Claydon flight have been completed successfully two days earlier than planned. The flight is now open to navigation.
23/10/2017 @ 11:03

Following further inspection, the replacement of the bottom gate at Claydon Top Lock 17 will be deferred until Winter 2019, thus releasing funds for other more urgent arising high priority works to be carried out this year. 

However, this closure will go ahead as planned, to enable the re-lining of both lock gates to prevent leakage. 

Description:

To undertake replacement of the bottom gate.

Location:
Oxford Canal
Starts At:
Lock 17, Claydon Top Lock
Ends At:
Lock 17, Claydon Top Lock
Up Stream Winding Hole:
Fenny Compton
Down Stream Winding Hole:
Below Claydon Bottom Lock 21