Railway Bridge 7, Lincoln
Detail
From Date: 24/06/2017 00:00
To Date: 24/09/2017 23:59 inclusive
Type: Navigation Restriction
Reason: 3rd Party Works
Is the towpath closed? No
Location
Closest waterway: River Witham
Starts at: Bridge 7
Ends at: Bridge 7
Description
AMEY on behalf of Network Rail are renewing the rail bridge beams.
There will only be overnight restrictions from 10pm to 5am.
Boaters will not be able to travel along this section during this time.
These works will not affect boat movements during daytime hours.
The dates these works are taking place are below:
24 June 2017 1 July 2017 8 July 2017 15 July 2017 22 July 2017 29 July 2017 5 August 2017 19 August 2017 26 August 2017 2 September 2017 9 September 2017 16 September 2017 23 September 2017 |
End date: |
25 June 2017 2 July 2017 9 July 2017 16 July 2017 23 July 2017 30 July 2017 13 August 2017 20 August 2017 27 August 2017 3 September 2017 10 September 2017 17 September 2017 24 September 2017 |