From Date: 19/02/2014 00:00

To Date: 11/04/2014 16:30 inclusive

Type: Advice

Reason: Maintenance

Is the towpath closed? Yes

Location

Closest waterway: Llangollen Canal

Starts at: Bridge 49, Knowles Bridge

Ends at: Bridge 50, Hampton Bank Bridge

Updates

04/04/2014 13:41

The navigation is now reopen today 4th April 2014 as scheduled. 

However, a 100m section of the towpath will remain closed for a further week whilst the contractors clear the site.  A temporary towpath diversion will be in place during this period.

14/02/2014 10:56

Due to the adverse weather on Wednesday 12th February 2014, there are a large number of trees blown down across the Llangollen canal which has closed navigation in a number of places.   We are working to clear the trees as quickly as possible, but to allow boaters currently trapped by the fallen trees to navigate through the Hampton Bank site, the navigation will not now be closed until Wednesday 19th February 2014.

Description

Due to a leakage on the embankment at Hampton Bank there is a risk of a possible breach and therefore emergency works are required.  Contractors will commence works on site on Monday 17th February to install piling on this section of canal.